PS 8 Rehabilitation Project

-Work within the pump station by Fleming Construction is complete.

-Street repairs to begin the week of May 21st.

-Ninth Street will be closed again for about 1-week.

-By-pass pump should be removed from operation by June 8th.

Sewer Pipeline Repairs – Gulf Coast Underground

-Contractor continues to work on yard restoration and clean-up throughout the project.

-Only two pipe repairs remain to be completed, one on Wilson near Soniat and the second behind 7701 Wilson.

-All concrete street repairs are complete.

-We have been promised that Wilson between Gordon and Roseland will be repaired this week.

-Substantial completion should be achieved this month, with final completion and restorations completing in mid-June.

Street Resurfacing Project

-Design for street resurfacing along VFW, Keilman, Prados, Marquette and East Sts. has been completed.

-“Piggy-Back” Contract with Barriere Construction is being signed this week (Jefferson Parish’s Annual Asphalt Contractor).

-Work will be performed between Jun 4th and August 3rd.

Pump Station 6 Rehabilitation and Rerouting.

-The design work is on schedule for completion in May with Bidding in June. 

-Construction work should begin in July and be complete by late 2018.

-This is the final contract to be funded by the State Clean Water Construction Program.

 

 

 

 
 